Developing Framework to Optimize the Preparation of (EOT) Claims Using Integration of (LPS) and (BIM) Techniques in Construction Projects

Article

Last updated: 04 Jan 2025

Subjects

-

Tags

Civil Engineering: structural, Geotechnical, reinforced concrete and s…nd sanitary engineering, Hydraulic, Railway, construction Management.

Abstract

Construction projects face delays and disturbances that could be caused by one of the contracting parties, both of them, or beyond their control. Proving the delay needs a significant effort to introduce all details, documents, and records which explain the causes of the delays. The contractor needs to submit a claim, whether it is extension of time (EOT) claim or any claim with an adequate definition, causation, liabilities, analysis of delays to get an extension of time-related to the risk event. Claims preparation processes need to be collected and documented daily throughout the project phases, especially during construction phases.
Lean Construction, with its common technique, the last planner system (LPS), and building information modeling (BIM) have significant synergies and can bring benefits when implemented together to support the preparation of the extension of time (EOT) claim. Building information modeling used as a digital platform to facilitate communication between the project team, improve project performance, and implement the last planner system (LPS) phases effectively. (LPS) is enhancing the coordination within the project team.
The primary purpose of the research is to develop Framework to Optimize the preparation of extension of time (EOT) Claims Using Integration of the last planner system (LPS) and building information modeling (BIM) Techniques in Construction Projects. The integration will represent in implementation of the appropriate (BIM) functionalities along with the five phases of the last planner system (LPS). As a result of the integration, the inputs and outputs well documented, which considered as the primary support to the processes preparation of the extension of time (EOT) claim. Also, The framework supported by process flowchart to clarify outputs, inputs, and the project team's responsibility, Which will contribute to optimizing the preparation of the extension of time (EOT) claims.

DOI

10.21608/jesaun.2021.169075

Keywords

lean, Building Information Modeling (BIM), Last Planner System (LPS), Extension of Time (EOT), Delay, Integration, Benefits, Weekly Work Planning (WWP), Percent Plan Complete (PPC), Daily Huddle Meeting, KanBim, kanban, 4D-Modeling, 3D-Modeling

Authors

First Name

Adel

Last Name

El-Samadony

MiddleName

-

Affiliation

Professor of Construction Engineering and Management- Civil Engineering Department- Helwan University- Cairo, Egypt

Email

ksamaster@epmcon.com

City

-

Orcid

-

First Name

Mohamed

Last Name

Tantawy

MiddleName

-

Affiliation

Assistant Professor of Construction Engineering and Management- Civil Engineering Department- Helwan University- Cairo, Egypt

Email

mtantawy@m-eng.helwan.edu.eg

City

-

Orcid

-

First Name

Mohamed M.

Last Name

Atta

MiddleName

-

Affiliation

MSc Candidate Construction Project Management- Faculty of Engineering Department- Helwan University- Cairo, Egypt

Email

mohamedatta324@gmail.com

City

-

Orcid

-

Volume

48

Article Issue

No 6

Related Issue

16952

Issue Date

2020-11-01

Receive Date

2021-05-05

Publish Date

2020-11-01

Page Start

1,196

Page End

1,221

Print ISSN

1687-0530

Online ISSN

2356-8550

Link

https://jesaun.journals.ekb.eg/article_169075.html

Detail API

https://jesaun.journals.ekb.eg/service?article_code=169075

Order

9

Type

Research Paper

Type Code

1,438

Publication Type

Journal

Publication Title

JES. Journal of Engineering Sciences

Publication Link

https://jesaun.journals.ekb.eg/

MainTitle

Developing Framework to Optimize the Preparation of (EOT) Claims Using Integration of (LPS) and (BIM) Techniques in Construction Projects

Details

Type

Article

Created At

23 Jan 2023